|

The following is a letter I received in reply to my concerns and those
raised by Gary Dean:
Dear Mr White,
I'd like to address some of the issues that you
have raised regarding the current works at part of the Glenrowan Revitalisation
project.
The remains of the "Stump" were
initially marked by the project archaeologist to ensure that it was not damaged
by workers during landscaping in the area. The stump was covered with a
piece of geotextile and then buried and the archaeologist has recorded the
location. The stump has not been moved or damaged in any way and it was
thought that this solution was the best passive conservation approach, which
will enable a suitable management decision to be made when the works are
completed.
With regard to the re-shaping of the creek line
running through the NW portion of the rail reserve. The battering, as I
understand it, is required for three reasons:
1. public
safety (previous formation had obscured and deep drops);
2. stability
- works further up the creekline means that water will enter this section at
greater force and the steep and unprotected banks would have eroded and
collapsed quicker that had occurred in the past;
3. maintenance
- the shallower batters reduce debris falling into the creekline and blocking it
and make it easier to access to slash grass etc.
The main point, however, is that the creek
alignment and soil deposits that made up the old banks were not original. Maps
of the site (1911) provided by Gary Dean, show that the drainage lines looked
very different to the present configuration. It is clear that the creek
was re aligned along the northern border of the rail reserve and was
straightened. The base of the creek was (and still is) a concrete V shaped
channel, sitting on a large (approx 1.8 metre wide) reinforced concrete slab
that runs the length of the creek line and under the so called original banks.
Observations made during the monitoring by the
project archaeologist suggest that the majority of material removed during the
battering exercise was derived and quite modern - of the very few artefacts
observed most were items such as crisp packets, batteries, MacDonald drinks cups
and straws etc. There was a low density of ceramic and glass frags but
they were in highly disturbed strata and also appeared to be of 20th century
date. There were no artefacts that could be attributed to the siege or to
that period or indeed considered to be in situ.
I understand that the creek will be lined
with geotextile and planted with native trees, shrubs and grasses as per the
original specs (plans and specs that have been in the public domain for a long
time). The main down side I think is that the battering works exposed the
artificial nature of the creek alignment and base. In my opinion, however,
the works have not significantly affected any historically 'pristine' landscape
or archaeological deposit and I believe that the appearance of the site will
improve greatly over the next 6 months.
I agree that it would be useful for Council to
have some plan or "artists impression" which would demonstrate to the
public how the site will look once the works are finished and established.
I would like you to be assured that a quality
archaeological process has been undertaken to protect the values of the site.
Heritage Victoria is very aware of the significant historical and archaeological
values of this place, and is working closely with the Council, community groups
and local owners to ensure positive outcomes for the site.
Regards,
Jeremy Smith
Senior Archaeologist
Heritage Victoria
7/8 Nicholson Street
East Melbourne 3002
Ph: 9637 9773
|